How to Perform Resource Management in Microsoft Project

How to perform Resource Management in Microsoft Project

The Resource Usage view in Microsoft Project displays the work hours performed by each resource. Once you’ve linked up your tasks in order of sequence and assigned a resource to each task, your Resource Usage view will show you the work scheduled for each worker or workers.

In the Resource Usage below, you can see a Painter has been flagged as over worked on an 8 hour day. He was assigned to paint the North Block and West block on the same day. He has 15.5 hours of work scheduled in one day. This is impossible for one Painter to achieve.

 

Your project plan has now identified a problem with your schedule. With the Painter over allocated, you have 2 options.

  1. You can assign an extra painter for that day to stay on track with the project schedule.
  2. Or you can delay one of the painting tasks to another day. This may extend the project finish date.

How do you know which option to take?

The Gantt Chart below is a construction schedule for a hospital. The red bars are critical tasks that need to start and finish on time, or it will delay the project finish date. If the Painting task is a red bar, then you would choose Option 1 – to add another worker.

But if the painting task is a blue bar, then you may choose Option 2 – to delay the task, which may not affect the project finish date.

 

 

By using Microsoft Project to plan your project, it will help you identify whether you actually need more resources on your project.

Receive the latest news in your email

Related Articles

  • What is Microsoft Project used for

    Microsoft Project advantages are more control and efficiency over time sensitive projects. It provides more control over the delivery of a project and provide a better forecast for your project. It

  • How to Perform Resource Management in Microsoft Project

    How to perform Resource Management in Microsoft Project The Resource Usage view in Microsoft Project displays the work hours performed by each resource. Once you’ve linked up your tasks in

  • Why do you need to know your Critical Path?

    The Critical Path is the longest path through your project and determines the end date of the project. Why is it important to know where your Critical Path is? If

  • What is Microsoft Project used for?

    What is Microsoft Project used for? Microsoft Project is used to plan out the work involved to achieve project goals. It helps you create a roadmap to the project goal

  • Who should attend Microsoft Project course

    Sed porttitor lectus nibh. Nulla quis lorem ut libero malesuada feugiat.

Speak to our Time Planners today

At Successful Projects, we seek to achieve the best outcomes for your project.

With offices in Perth and Canberra, our team of project planning experts work with the support of a highly experienced internal team, working together to secure your desired outcomes.