The tender requirements for the FMG Mining Processing plant included design, procurement and construction of three iron ore processing plants. We worked with the design, procurement and estimation team to prepare a detailed project schedule to demonstrate our client’s ability to successfully deliver the project in the timeframe available.
Role
Our role was to prepare a detailed, fully resourced, fully costed project schedule including all design activities, procurement of tagged equipment, fabrication assembly, shipping and delivery of plant modules to site from site based civil works, construction, module installation and commissioning. This schedule allowed for analysis of resourcing constraints and accommodation requirements.
Outcomes
The detail in our schedule allowed for optimising resource by smoothing resource peaks and reduce construction risk. The schedule was used to perform what-if analysis of the impact of changes to procurement and shipping and analysis of project risks and opportunities for reducing the project timeline.